What is the lot sizing technique that generates exactly what was required to meet the plan a Wagner Whitin B Economic Order Quantity c lot for periodic order quantity?

This activity contains 17 questions.


The list of quantities of components, ingredients, and materials required to produce a product is the


 


____________ allows a segment of the master schedule to be designated as "not to be rescheduled."


 


A lot-sizing technique that generates exactly what was required to meet the plan is


 


Breaking up the order and running part of it ahead of schedule is known as


 


The difference between a gross material requirements plan (gross MRP) and a net material requirements plan (net MRP) is


 


A phantom bill-of-materials is a bill-of-materials developed for


 


Which of the following lot-sizing techniques is likely to prove the most complex to use?


 


When a bill-of-materials is used in order to assign an artificial parent to a bill-of-materials, it is usually called a


 


The operations manager has several tools available to deal with MRP system nervousness. Those tools are


 


An MRP system that provides feedback to the capacity plan, master production schedule, and production plans is called


 


A time-phased stock-replenishment plan for all levels of a supply chain is called


 


Which of the following is an advantage of ERP?


 


Use the product structure tree and the inventory records to determine how many item Cs should be ordered in order to produce 20 phones.

Item On-Hand
A 5
B 5
C 5
D 25
E 4
F 20

 


Use the product structure tree and the lead time information (in weeks) to determine when an order for Fs should be placed to deliver phones in week 10 if the phones require 2 weeks to assemble. Assume there is no starting inventory for any component or end item.

Item Lead Time
A 2
B 1
C 3
D 2
E 3
F 2

 


A(n) ________ system provides feedback to the capacity plan, master production schedule and production plan.


 


Which of these pieces of information is NOTcontained in a bill of material?


 


A report that shows the resource requirements in a work center for all currently assigned work as well as all planned and expected orders is a


 

Answer choices in this exercise appear in a different order each time the page is loaded.

What is the lot sizing technique that generates exactly what was required to meet the plan Part 2?

A lot-sizing technique that generates exactly what was required to meet the plan is. the Wagner-Whitin algorithm.

When the setup cost is low which lot sizing technique is the most appropriate?

Periodic lot sizing procedures are effective when used with cheap items when inventory cost is low. 5.

What lot sizing technique is generally preferred when inventory holding cost are extremely high?

Question: What lot-sizing technique is generally preferred when inventory holding costs are extremely high? lot-for-lot EOQ.

What is the information system used for identifying and planning the enterprise wide resources needed to take make ship and account for customer orders?

Enterprise Resource Planning: An accounting oriented information system for identifying and planning the enterprise-wide resources to make, ship and account for customer orders.”