Which of the following best describes a kill point in the project life cycle?

25 Questions | Total Attempts: 2201

  • The project life cycle is comprised of which of the following?

  • Marcy, the project manager for the ERP Project, is about to complete the project phase review. The completion of a project phase is also known as which of the following?

  • Which of the following is not a key stakeholder in a project that creates a service internal to an organization?

  • Of the following management skills, which will a project manager use most?

    • Influencing the organization

  • Managing a project is best described as which one of the following?

    • Functional controls over the project team and stakeholders

    • Consistently producing key results expected by stakeholders

    • Motivating and inspiring the project team to produce results that are expected by project stakeholders

  • When will stakeholders have the most influence over a project's product?

    • At the end of the project

    • During scope verification

    • At the start of a project

    • At the start of each phase

  • Which of the following is an example of negotiation?

  • You are the project manager for your organization. Influencing your organization requires which of the following?

    • An understanding of the organizational budget

    • Research and documentation of proven business cases

    • An understanding of formal and informal organizational structures

  • Your global project is sabotaged by rumors and gossip about the project deliverable. This is an example of:

    • Cultural influences within the project team

  • What is the difference between a standard and a regulation?

    • Standards are mandatory; regulations are not.

    • Standards are optional; regulations are not.

    • Regulations and standards are essentially the same.

    • Regulations are usually mandatory; standards may be seen as guidelines.

  • All of the following are examples of stakeholders that have a positive influence on a project except for which one?

    • Business leaders in a community affected by a commercial development project

    • Team members that will receive a bonus if the project is successful

    • Employees that prefer the older version of the software that a project is replacing

    • Functional managers that want your project to complete so their employees can move onto other projects

  • Which of the following is an example of a deliverable at the end of the requirements-gathering phase in a software design project?

    • Responsibility matrix creation

  • You are the project manager for the ERP Project. Your organization uses a PMO. The primary purpose of a project office is to:

    • Support the project managers

    • Support the project sponsor

    • Identify the stakeholders

  • Which of the following best describes a project deliverable?

    • The resources used by the project to complete the necessary work

    • The resources exported from the project as a result of the project work

    • The end result of a project planning session

    • The tangible good or service created by the project team

  • At what point in a project would a kill point be acceptable?

    • When a project team member is not performing as planned

    • When a project reaches the end of a project phase

    • When a project reaches the end of its budget

    • When a project manager determines the project team cannot continue

  • Of the following, which is not an exit criterion?

  • The compilation of all the phases within a project equates to

  • Management has asked Nancy to determine if a project concept is valid and can be completed using a reasonable amount of time and finances. Management is asking for which of the following?

  • Henry, the project manager of the MHB Project, has allowed a subsequent project phase to begin before the predecessor phase is complete. This is an example of which of the following?

  • Which of the following describes the early stages of a project?

    • High costs and high demand for resources

    • A high demand for project team time

    • Low costs and low demand for resources

  • At which point is the risk of failure the least but the consequence of failure the highest?

    • Risk of failure is even across all project phases

  • Tracey is the project manager of the KHG Project. Her organization is a classic functional environment. Her level of authority as a project manager can be best described as which of the following?

  • Project team members are most likely to work full-time on a project in which of the following organizational structures?

  • A project with much risk and reward is most likely to be accepted in which of the following?

    • An entrepreneurial company

    • A heavily regulated company

  • Where can a project manager expect to receive templates?

    • Project Management Information System (PMIS)

  • Love
  • Destiny
  • Sad
  • Survival

The project life cycle is comprised of which of the following?A. PhasesB. MilestonesC. Estimates

D. Activities

Marci Koening, the project manager for the ERP Project, is about to complete the project phase review. Thecompletion of a project phase is also known as which of the following?A. Lessons learnedB. Kill pointC. Earned value management

D. Conditional advancement

Which of the following best describes a project deliverable?A. The resources used by the project to complete the necessary workB. The resources exported from the project as a result of the project workC. The end result of a project planning session

D. A verifiable, measurable work product

The compilation of all the phases within a project equates to the ____________________.A. Project life cycleB. Product life cycleC. Project completion

D. Project processes

Which of the following describes the early stages of a project?A. High costs and high demands for resourcesB. A high demand for changeC. A high demand for project team time

D. Low costs and low demands for resources

At which point is the risk of failure the lowest, but the consequence of failure the highest?A. During the early stagesB. During the middle stagesC. During the final stages

D. Risk of failure is even across all project phases

Project team members are most likely to work full-time on a project in which of the following organizationalstructures?A. FunctionalB. Weak matrixC. Strong matrix

D. Projectized

Why would an organization divide a project into phases?A. To provide better management and control of the projectB. To identify the work that will likely happen within a phase of the projectC. To identify the resources necessary to complete a phase of the project

D. To define the cashflow requirements within each phase of the project

All of the following are true statements about the project life cycle, except for which one?A. The project life cycle defines the work to be done in each phase of the projectB. The project life cycle defines the deliverables that each phase will createC. The project life cycle defines who is involved in each phase

D. The project life cycle defines how much each phase will cost

You are the project manager of a new project. When is the level of failing to achieve the objectives thehighest within your project?A. There is not enough information provided to know for certainB. At the start of the projectC. At the end of the project

D. During the intermediate phases of the project

Which one of the following is an example of a positive stakeholder?A. The comptroller within your organizationB. A customer who is eager for your project's deliverableC. An environmental group that has claims against your project

D. A union

None of the following are key project stakeholders, except for which one?A. UnionB. InfluencerC. Technical interface

D. Inspector

You are a project manager acting in a functional organization. The functional manager and you disagreeabout several deliverables the project will be creating. The functional manager insists that you begin theproject work now. What must you do?A. Begin workB. Resolve all of the issues with the functional manager before you begin workingC. Continue planning, as you are the project manager

D. Begin work as long as the issues don't affect the project deliverables

You are a project manager working under a PMO. Your project resources are shared among severalprojects. To whom will the project team members report?A. The project manager of each projectB. The functional managersC. The PMO

D. The project manager of their primary project

At what point in the project may stakeholders most cost-effectively recommend changes to the projectdeliverable?A. Before the project charter is createdB. At the start of the projectC. During the intermediate phases

D. During the final phase of the project

An organization has elected to kill a project. When is this decision most likely made?A. At the end of a phaseB. At the start of a phaseC. When the project is not meeting its financial requirements

D. When technology has superseded some of the technology used within the project

Nancy is a project manager for the NHG Corporation. She has identified several positive stakeholders for herconstruction project and a few negative stakeholders. Nancy and the project team have been meetingregularly with the positive stakeholders, but have not met with the negative stakeholders. What can happen ifNancy ignores negative stakeholders?A. Her project will likely succeed without any objectionsB. Her project may suffer poor political capital from the negative stakeholdersC. Her project will risk failure to bring the project to a successful end

D. The negative stakeholders will not have an opportunity to communicate with the project manager

All of the following are cultural attributes of an organization, except for which one?A. Policies and proceduresB. Work ethicsC. View of authority relationships

D. Experience of the project management team

The project management plan defines which one of the following?A. Who the project manager will beB. How the project manager will use the project management systemC. When the project team will be assembled and released

D. How the deliverable will be shipped to the customer

Who has full authority over project funding in a weak matrix?A. The project managerB. The functional managerC. The PMO

D. The project sponsor